Bridge Construction Begins June 2, 2021

by Colleen Paveglio
Friday, May 28, 2021

May 28, 2021 -  Through careful planning, the City of Traverse City is preparing to begin major bridgework throughout the City on June 1, 2021. The infrastructure improvements will include the bridges on Park Street, S. Cass Street and E. Eighth Street. 

City staff is coordinating the project with MDOT’s Traverse City TSC and Local Agency Bridge program, the City’s municipal utilities, DDA, and public services, State and Federal agencies, and property owners, and water recreation businesses. The project is being funded by the MDOT Local Bridge Fund ($3.9 Million), City Funds ($294,000), City Municipal Utility Funds ($383,000), and DDA TIF Funds ($432,000). 

"The upcoming bridge work is critical to maintaining our infrastructure within the City. Staff has worked diligently on preparing for these major bridge projects for the City's future.  We are pleased to have funding assistance from various sources to invest in infrastructure and develop increased amenities such as pedestrian lighting and wider sidewalks,” says City Manager Martin Colburn

 

Park Street Bridge

Beginning June 2, 2021, site preparation will begin for the Park Street Bridge. The project will include the construction of new bridge deck and an increased sidewalk width to 9.5’ from the existing width of 6’ – 4 ½”. Pedestrian scale lighting and traditional streetscape will be included in the project. The Parks Street Bridge project is anticipated to be completed in November 2021.

 

S. Cass Street Bridge

The S. Cass Street Bridge construction is anticipated to begin construction on June 14, 2021. The project will include bridge removal and replacement.  Amenities include a decorative pedestrian railing and traditional streetscape. An effort to maintain the historic character of the original bridge through the rehabilitation to remove the wood sidewalk and railing will be made.  The S. Cass Street Bridge project is anticipated to be completed in November 2021.

 

E. Eighth Street Bridge

The E. Eighth Street Bridge construction is anticipated to begin construction on July 26, 2021. The project will include the replacement of the bridge deck and extension of a watermain transmission line. Additional amenities incorporated into the project include the extension of the cycle track to connect with the existing bike lanes, increased width of the sidewalk, decorative railings, and an aesthetic double arch fascia. The sidewalk under the bridge will be elevated and lighting will be installed. The E. Eighth Street Bridge project is anticipated to be completed in November 2021.

"The bridges throughout the City are in need of maintenance and repair.  While the construction season is upon us, we can work together to navigate through the City with patience to create a safe environment for motorists, pedestrians, City staff, and contractors within these work zones," says Mayor Jim Carruthers.

The construction will generate dust and noise. Traffic delays are expected and detour maps have been developed to assist those traveling throughout the City. Pedestrians will be directed to use the Cass Street tunnel to access Clinch Park and the Open Space. The Boardman River will be closed to traffic during the weekdays and open on the weekends as much as possible.

“The Downtown Development Authority appreciates the partnership in starting this important bridge infrastructure work for our entire region.  The bridge repair work, though disruptive to vehicles, is a much needed infrastructure improvement that will be both an aesthetic and logistical enhancement to our downtown community,” says DDA CEO Jean Derenzy.

 

The Downtown Development Authority will hold two informational zoom sessions to discuss upcoming bridge projects on Park, Cass, Eighth, and Front Streets and how this construction will affect Downtown Traverse City. Both sessions will have a question-and-answer session, as well as an explanation of the proposed detour routes.

 

The first session will take place at 9am on Wednesday, June 2, 2021.

Link to the Zoom Session:

https://us02web.zoom.us/j/89882874449?pwd=eE9lcUppa0s2ZFB1R0NXdXJTaFFIZz09

Meeting ID: 898 8287 4449

Passcode: 045027

One tap mobile +13126266799,,89882874449#,,,,*045027# US (Chicago)

+16465588656,,89882874449#,,,,*045027# US (New York)

 

The second session will take place at 3pm on Thursday, June 3, 2021.

Link to the Zoom Session:

https://us02web.zoom.us/j/81982189247?pwd=ZndxSnR2eVBvaGNGdllvNk9jcW9YUT09

Meeting ID: 819 8218 9247

Passcode: 830337

One tap mobile +13126266799,,81982189247#,,,,*830337# US (Chicago)

+16465588656,,81982189247#,,,,*830337# US (New York)

 

To learn more about upcoming bridgework and view project updates and detour information, visit https://www.traversecitymi.gov/bridgework.asp